End of a 116-year era for Transnet

Grindrod has become the first private company to run a train on South Africa’s national freight rail network under the new open-access framework, marking the end of Transnet’s 116-year monopoly.

The logistics group completed a successful test run with Transnet Rail Infrastructure Manager (TRIM) on the North-East Corridor in November 2026.

The operation marks a major step in allowing private companies to use the state-owned rail network.

The test began in Komatipoort, Mpumalanga, on 1 November. The train travelled empty before returning on 2 November carrying 2,991 tonnes of cargo.

The operation used Grindrod-owned locomotives and wagons, demonstrating the company’s readiness to run services on the corridor.

Grindrod was among 12 train operating companies that signed rail access agreements with Transnet. These agreements give private operators access to the national freight rail network.

The company plans to start commercial services in 2027, with 288,000 tonnes of cargo targeted in its first year.

It has been allocated two slots on the North-East Corridor and will mainly transport coal from Mpumalanga to its Matola Terminal in Mozambique.

Further growth will depend on available capacity, additional train slots and operational efficiencies.

The agreement will allow Grindrod to connect its rail operations more closely with its existing port and terminal infrastructure. The group operates an integrated logistics business linking customers to regional and international markets.

The North-East Corridor is an important route between South Africa’s mining and industrial areas and regional markets and export facilities.

Using its own trains on the network could help Grindrod improve the efficiency and reliability of its logistics services.

Grindrod Group CEO Kwazi Mabaso explained that the test demonstrated the practical value of rail reform.

“As an integrated logistics provider, the ability to combine rail operations with our terminal infrastructure and corridor footprint enables us to deliver greater efficiency, reliability and value to our customers.”

He said the company was proud to work with TRIM to help restore rail as the backbone of bulk freight transport.

Transnet also described the test as an important step in moving its open-access policy into practice.

TRIM chief executive Moshe Motlohi said the successful operation was a landmark for South Africa’s rail reform programme. “It demonstrates that open access is no longer a policy concept but an operational reality.”

He added that working with private operators would help create a more competitive and efficient rail network.

The test also provides an example of how private operators could help improve the use of the existing network and shift more freight onto rail.

Transnet is opening its network to private companies

Grindrod’s test run forms part of Transnet’s wider effort to attract private investment and expertise into its rail and port operations.

The state-owned logistics company has faced years of falling freight volumes, underinvestment, operational challenges and financial pressure.

Its recovery strategy, introduced under CEO Michelle Phillips in October 2023, aims to improve performance across its rail, port and pipeline businesses.

Transnet reported revenue of R88.56 billion for the 2025/26 financial year. This represents an increase of 7.1%.

It also recorded a profit of R4.6 billion, its first full-year profit since 2022/23. This followed a R1.9 billion loss in 2024/25 and a R7.3 billion loss in 2023/24.

The improved result was supported by higher rail and pipeline volumes, tariff adjustments and better operational performance.

However, the sale of Transnet’s interest in Durban Container Terminal Pier 2 also played a part in this result.

The company has also received significant government support. National Treasury provided a R47 billion financial guarantee in December 2023, followed by another R51 billion guarantee in May 2025.

Despite its improved financial performance, Transnet is increasingly relying on private companies to help finance, operate and upgrade its infrastructure.

One example is its agreement with Philippines-based International Container Terminal Services Inc. (ICTSI) for Durban Container Terminal Pier 2.

Signed in December 2025, the agreement allows ICTSI to acquire an almost 50% stake in the terminal for R10.5 billion and manage the facility for 25 years.

The terminal handles approximately 70% of the Port of Durban’s total throughput and 40% of South Africa’s container volumes.

Transnet is also looking for a private partner to help expand and operate the Ngqura manganese export corridor.

The project could cost up to R44 billion and would link mines in the Northern Cape with ports in the Eastern Cape.

The proposed expansion is part of Transnet’s broader private-sector participation programme which aims to attract private investment and use external expertise to improve the performance of the country’s logistics infrastructure.

You have read 1 out of 5 free articles. Log in or register for unlimited access.

  1. kgomotso3
    21 November 2026 at 18:00

    Another SOE corrupt Mismanagement Maladministration piece, frauters to be taken to the account to Law first, those who stole from it to return the money 💸💰 to public purse before privatisation.

    Thank you 💕😊👌.