The government paid R371 million for a Mega Housing Project but no housing units have been completed

The government paid R371 million to contractors and service providers for a Mega Housing Project, but no housing units have been completed.

This was revealed by the Minister of Human Settlements, Thembi Simelane, in response to a Parliamentary question by National Assembly member Zelna Abader.

Abader asked Simelane for details about the Tembisa Extension 25 Mega Housing Project that was intended to deliver 3,510 housing units.

Numerous reports indicate that the housing project has been stalled since 2021 despite millions of rands having been paid.

Abader requested details on the originally approved budget and the amount paid to contractors and service providers to date.

She also asked for details about the completed housing units which have been certified and handed to beneficiaries.

Abader further wanted to know what disciplinary, civil, or criminal action has been instituted against any responsible official or contractor.

Simelane responded, saying the Gauteng Department of Human Settlements approved a budget of R1.4 billion for the Tembisa Extension 25 Mega Housing Project.

“Approximately R371 million has been paid to contractors and service providers to date,” she said.

“No housing units have been completed, certified as complete or transferred to beneficiaries.”

She said that 380 housing units remain incomplete at various stages of construction and have been vandalised.

The minister further revealed that the extent of losses linked to this project has not been accurately quantified.

No disciplinary, civil, or criminal action against those responsible

Minister of Human Settlements, Thembi Simelane

Simelane said that no disciplinary, civil or criminal action has been instituted against officials or service providers.

“Records relating to project management, payment authorisations and certification are available,” she said.

“However, the City of Ekurhuleni has indicated that the officials responsible have since left its employ.”

The Minister added that the City of Ekurhuleni attributed the incomplete construction and vandalism to funding shortages rather than misconduct or negligence.

“According to the provincial report, construction activities were halted by disruptions due to construction mafias operating under the guise of a business forum,” she said.

The City of Ekurhuleni further cited funding constraints and budget reductions as factors that prevented the completion of construction.

These funding and budget constraints were also blamed for the failure to repair infrastructure damaged by vandalism.

“These factors contributed to the prolonged stoppage and deterioration of the incomplete development,” Simelane said.

She explained that the development comprises RDP walk-up blocks rather than individual residential stands.

“Six blocks are reported to be in moderate condition, while five have deteriorated severely,” she said.

“An additional R82 million is required to complete the housing units in the blocks assessed as being in moderate condition.”