The province in South Africa Parliament warns risks bankruptcy

Delays in completing ever-increasingly expensive infrastructure projects and shoddy work by contractors risks bankrupting the Mpumalanga province.

This is the warning from a joint delegation of Mpumalanga permanent delegates to the National Council of Provinces (NCOP) and Members of the Provincial Legislature (MPLs).

ANC MPL Ngrayi Ngwenya stated that the province is losing money due to project completion delays in a completely unsustainable manner.

This often results in cost escalation and forces the provincial government to allocate additional funding to correct structural defects by shoddy contractors.

“Government is working backwards; this wastage will bankrupt our province,” said Ngwenya.

The MPL used their recent oversight visit to the Mpumalanga High Altitude Training Centre (MHATC) in the Emakhazeni Local Municipality as an example.

The MHATC is a sporting academy which will have all sporting codes promised to enhance the competitiveness of athletes and boost sport tourism in the Mpumalanga province.

The total cost of the entire project is estimated at R450 million of taxpayer funds. It is overseen by provincial Departments of Public Works and Transport and Sports, Arts and Culture.

The scope of the MHATC project consists of construction, bulk water pipelines from the treatment plant to the new 7Ml reservoir and to the MHATC, a new 7 megaliter concrete water reservoir, bulk sewer mains and pump stations, bulk electrical infrastructure, and roads infrastructure.

While the reservoir is expected to be completed in March next year, there has been little progress in the construction of the waste water treatment plant, with R29 million of the total R82 million spent so far.

Ngwenya lamented the cost escalations and structural defects by shoddy contractors.

“There are also many examples of leaking water reservoirs across the province that cannot be used and require additional funding to be fixed,” said Ngwenya.

The delegation also heard that the existing wastewater treatment plant is not performing to the required standards, which leads the municipality to release untreated effluent into the natural environment.

“Environmental non-compliance, such as releasing untreated effluent into our rivers and streams, is criminal. This situation must be urgently addressed,” said NCOP permanent delegate Sonja Boshoff.

Acting delegation leader Patrick Sibande called for better planning and budgeting, as well as improved monitoring and evaluation.

Sibande also condemned the late payment of contractors over the stipulated 30-day period, which has contributed to the delays.

One of the incomplete projects. Photo: Supplied/ Mpumalanga provincial legilature

Projects are ‘going to be world class’

Morake Morolo, the head of department for the provincial Department of Public Works and Transport, said that “it is going to be world class and would include a sports academy with all the sporting codes, a boarding school, entertainment areas and a hotel.”

“The altitude in the area is one of the best. Feasibility studies show that this is a viable concept and will attract international athletes.”

Responding to members’ concerns about the delays, Morolo said that ‘not all delays were bad and that good things take time.’

His counterpart from the Department of Culture, Sport and Recreation, Mxolisi Mahlangu, said the project has been spread over years due to a limited budget, but each fiscal year the department allocates funds toward the project.

Auditor General’s red flags

The Auditor-General of South Africa’s latest audits reinforce the NCOP’s warnings that Mpumalanga’s infrastructure challenges are part of a broader national governance crisis.

Annual MFMA and PFMA findings repeatedly flag delays, poor workmanship, and weak financial controls in the province’s projects: problems that threaten to strain Mpumalanga’s R66 billion budget.

According to the AGSA’s 2023-24 MFMA Consolidated General Report, 87 of 113 audited infrastructure projects nationwide had significant findings, largely due to poor planning, inadequate maintenance, and non-compliance.

Nationally, only 13% of municipalities achieved clean audits, while irregular and fruitless expenditure climbed into the billions, driven by non-competitive procurement and poor contractor oversight.

These trends mirror Mpumalanga’s own problems: unusable reservoirs, failing wastewater plants, road and hospital overruns, and long-stalled capital projects such as the High Altitude Training Centre.

The AGSA warns that project delays, affecting 52% of audited infrastructure, are a major source of cost escalation, while poor workmanship continues to force expensive rework.

Overspending remains acute in infrastructure-heavy departments, with the national fruitless expenditure tally reaching R4.74 billion.

Mpumalanga’s fiscal pressures are compounded by municipal debt and chronic under-maintenance of water systems.

Though some municipalities have improved through provincial interventions, the AGSA notes that systemic weaknesses persist.

It recommends stronger internal controls, timely reporting, enforcement of contractor penalties, and better monitoring of infrastructure spend: areas directly aligned with the NCOP’s calls for tighter planning and accountability.

You have read 1 out of 5 free articles. Log in or register for unlimited access.
  1. cikdrone
    26 November 2025 at 15:33

    This is exactly what you get when the Government insists on using BEE Contractors that do not have the skill or equipment to get the work done on time and on budget.
    So another waste of Taxpayers money.

9 months on – South African refugees in the United States face an uphill battle

16 Feb 2026

New board for state-owned enterprise struggling to pay salaries

16 Feb 2026

Top economist positive about Cyril Ramaphosa’s State of the Nation Address

16 Feb 2026

Expect to get killed if you point a gun at a soldier in Cape Town or Gauteng

16 Feb 2026

Water Minister in Ethiopia amid crisis, and ex-city manager’s R3.5 million luxury trip exposed

16 Feb 2026

One man warned about South Africa’s water crisis 18 years ago – and was suspended

16 Feb 2026

Ramaphosa gives false hope about water crisis

15 Feb 2026

South Africa’s democratic crisis

15 Feb 2026

From unemployed graduate to top olive oil entrepreneur

15 Feb 2026

President Ramaphosa tells a good story while the country collapses

14 Feb 2026